Banyan High Point

A partnered approach that delivered an early finish.

Garrett Construction served as third-party general contractor for Banyan Residential on this 399-unit, six-building community in Aurora, Colorado. Working side by side with the owner, and with four Garrett affiliates on the job, our team finished ahead of schedule.

View the Community
  • 399Units
  • 512,000Sq. ft.
  • 5 of 6Buildings early
  • Up to 14Weeks ahead of schedule

The Project

Six low-rise buildings with 399 market-rate homes, built for Banyan Residential and its equity partner Bridge Investment Group.

Banyan High Point, photo 1 of 51 / 5
Banyan High Point, photo 2 of 52 / 5
Banyan High Point, photo 3 of 53 / 5
Banyan High Point, photo 4 of 54 / 5
Banyan High Point, photo 5 of 55 / 5
OwnerBanyan Residential, with equity partner Bridge Investment Group
Garrett’s RoleThird-party general contractor
LocationAurora, Colorado
Units399
Buildings6 (one 4-story, five 3-story)
Square Feet512,000
ProductLow-rise, market rate
ArchitectW Partnership
TimelineBroke ground June 2023; first certificate of occupancy February 2026; final expected November 2026
Affiliates on the JobApex Lumber & Materials, Blue Horseshoe Framing, Blue Star Mechanical, Teldar Drywall & Paint

How We Delivered Ahead of Schedule

Owners remember how a contractor responds when a schedule comes under pressure. At Banyan High Point, we treated the schedule as a shared commitment and gave Banyan Residential clear, regular updates at every step.

The Challenge

Banyan High Point depended on off-site utility and road infrastructure delivered by the community’s master developer. Coordinating that work among the owner, the master developer and local agencies added complexity early in the project, and framing could not begin until utilities and roads reached the site.

What We Did

We worked closely with Banyan Residential and the master developer to track the off-site work and plan around it. While we waited, our team poured every building slab, finished all on-site utilities, built the elevator shafts and staged the site so framing could start at full speed. Once it could, we added crews across every trade. Our affiliates made the difference:

  • Apex Lumber & Materials expedited lumber deliveries so framing never waited on material.
  • Blue Horseshoe Framing ramped up framing crews the moment work could begin, under the direction of Garrett superintendents.
  • Blue Star Mechanical bought plumbing and HVAC equipment well ahead of schedule, managed its storage and added crews to speed installation.
  • Teldar Drywall & Paint ran multiple crews in several buildings at once without compromising quality.

The Result

An early finish: five of the six buildings were delivered ahead of schedule, one by 14 weeks.

Partner With Garrett

Let’s talk about your next project.

Tell us about your next multifamily project, and our construction team will follow up to talk through budget, schedule and how Garrett can help bring it to completion.

Start a Conversation
Next case study

Aspire on 10th

Sarasota, Florida Coming Soon